Example SWMS

Commercial Electrical Installation

Generated in 43 seconds

Document Information

Document TitleSWMS — Commercial Electrical Installation and Fit-Out
Document No.SWMS-ELC-2026-029
RevisionRev 1.0
Date7 March 2026
Prepared BySafeMethod AI
Site LocationLevel 2, 55 Queen St, Auckland — Office fit-out
Workers4 (1 Supervising Electrician, 2 Electricians, 1 Apprentice)
Duration3 weeks

Scope of Work

Complete electrical installation for a commercial office fit-out on Level 2 of an existing multi-storey building. Work includes distribution board installation, sub-main cabling from the building main switchboard, cable tray and conduit installation in the ceiling void, power outlet and data cabling, lighting circuit installation, and fire alarm interface. Building main switchboard remains live throughout — all new work is installed dead and connected live at final stage only.

Work Sequence

Exclusions

This SWMS does not cover modifications to the building main switchboard (requires network operator coordination), UPS or generator installation, or fire alarm panel programming.

Legislation & Standards

Hazard Analysis

Hazard Inherent Risk Control Measures Residual Risk
Electric shock
Contact with live conductors at the building main switchboard (400V 3-phase) during sub-main connection, or with existing live circuits in ceiling void
4 x 5 = 20 Extreme Elimination All new installation work completed dead — circuits only energised at final commissioning stage after full testing
Engineering Lock-out/tag-out (LOTO) on circuits being worked on; voltage tester used to confirm dead before touching conductors
Administrative Only licensed electricians to work on or near live equipment; live work risk assessment and permit for final connection at main switchboard
PPE 1000V rated insulated gloves, insulated tools, and safety footwear with electrical hazard rating
2 x 5 = 10 High
Arc flash
Electrical arc explosion at main switchboard during live connection — temperatures exceeding 19,000 degrees C, blast pressure, and molten metal ejection
3 x 5 = 15 High Elimination Where possible, arrange a planned shutdown with building management to connect sub-main dead
Engineering Arc-rated switchboard with internal barriers between bus sections; use insulated tools and cable covers
Administrative Arc flash risk assessment completed; exclusion zone around switchboard during live connection; only one electrician at the panel
PPE Arc-rated face shield (minimum 8 cal/cm2), arc-rated clothing, and insulated gloves during live switchboard work
1 x 5 = 5 Medium
Falls from height
Working from ladders and mobile scaffolds to access ceiling void (~3m); risk of fall during cable tray installation and cable pulling
4 x 4 = 16 High Substitution Use mobile elevating work platform (scissor lift) instead of ladders for extended ceiling void work
Engineering Mobile scaffold with guardrails and locking castors for workstation-based tasks (fitting, terminating)
Administrative Ladders only for brief access (under 15 minutes); 3-point contact rule; ladder inspected before each use
Administrative Workers trained in MEWP operation; daily pre-start inspection of scissor lift
2 x 4 = 8 Medium
Cable pulling injuries
Musculoskeletal injuries from pulling heavy sub-main cables through conduit and cable tray; hand/finger crush between cable and tray edges
4 x 3 = 12 High Engineering Cable winch or tugger used for sub-main cable pulls (cables over 25mm diameter); cable lubricant to reduce friction
Engineering Cable rollers and guides at tray bends to prevent cable snagging
Administrative Team pull with communication between puller and feeder; stop if cable resistance is excessive
PPE Rigger's gloves to protect hands from cable edges and tray burrs
2 x 3 = 6 Medium
Fire
Electrical fault causing fire in distribution board or cabling; overloaded temporary supply during fit-out phase
3 x 4 = 12 High Engineering All circuits protected by correctly rated circuit breakers and RCDs as per AS/NZS 3000; RCD testing before energisation
Engineering Fire extinguisher (CO2 type — suitable for electrical fires) within 5m of distribution board
Administrative All connections torqued to manufacturer specification to prevent loose connections and arcing; IR scan of DB after energisation
Administrative Temporary construction power board with RCD protection for all power tools during fit-out
1 x 4 = 4 Low

Emergency Procedures

Assembly PointGround floor lobby, 55 Queen St (building evacuation point)
First AidFirst aid kit on Level 2 site; AED in ground floor lobby
First AiderJ. McLeod (Supervising Electrician) — current first aid certificate including CPR/AED
Emergency Services111
Nearest HospitalAuckland City Hospital — 10 min drive
Building ManagerBayleys Property — 09 555 0189

Electric Shock

Do not touch the person if they are in contact with the live source. Isolate the supply at the nearest switchboard or emergency stop. Call 111. Commence CPR if the person is unresponsive and not breathing. Use the AED from the ground floor lobby. Do not delay CPR while waiting for the AED.

Arc Flash Incident

If an arc flash occurs, isolate the supply immediately. Move the casualty away from the switchboard. Call 111 — request ambulance for burn injuries. Cool any burns under running water for 20 minutes. Do not remove clothing fused to skin. All arc flash incidents are notifiable to WorkSafe NZ.

Sign-Off

All workers must read and understand this SWMS before commencing work. By signing below, each worker confirms they have been briefed on the hazards, controls, and emergency procedures, and agree to follow them.

J. McLeodSupervising Electrician — _______________
R. WattsElectrician — _______________
L. SharmaElectrician — _______________
C. BrownApprentice Electrician — _______________

Generate Your Own Electrical Work SWMS

Describe your electrical installation or maintenance task and get a complete SWMS with isolation and arc flash controls in under 60 seconds.

Get Started Free